Outdoor Irrigation Schedule.
To ensure that your drinking water is safe and potable, Little Bear has implemented a number of programs to comply with existing federal and state laws and regulations. A few of the programs are listed below:
- Monthly Coliform Sampling and Testing - Little Bear's monthly coliform monitoring sampling and testing results is as of this month reporting as "absent" which include testing of its raw source (Well No. 3).
- Stage 2 Disinfection Byproduct Sampling and Testing - Sampling and testing of the designated two sites that are located at the end of Little Bear's distribution system, test results meets both federal and state standards.
- Lead and Copper Sampling and Testing - The district Lead and Copper Program, in which tap samples are taken from selected residential homes (10), meets federal and state standards.
- Asbestos Sampling and Testing - Little Bear's quarterly sampling and testing for asbestos for designated sites within the distribution system, test results were reported as "none detected."
- Hexavalent Chromium Sampling and Testing - The requirement that water utilities test their raw source(s) (at the well) for Hexavalent Chromium, all reported initial results was reported as "none detected.
In addition to better serving you, our customers, Little Bear will ensure the safety of its drinking water through monthly sampling and testing for the following:
MonthJanuary
February March April May June July August September |
Nitrate7
6 6 6 6 6 6 6 7 |
TDS332
345 325 332 332 324 330 356 336 |
PH7.2
7.0 7.4 7.2 7.2 7.0 7.1 7.2 7.2 |
Sodium32
31 Not Tested 30 31 61 31 31 33 |
Sulfate82
78 78 78 77 75 76 76 77 |
Ammonia0.13
0.20 0.39 Not Tested Not Tested Not Tested Not Tested Not Tested 0.16 |
Up-dated: October 24, 2014
Hardness Reported As: 12 Grains Per Gallon
In its continuing effort to keeping you inform, the following information on it source production to support district daily water demand and peak demands are provided:
Hardness Reported As: 12 Grains Per Gallon
In its continuing effort to keeping you inform, the following information on it source production to support district daily water demand and peak demands are provided:
MonthJanuary
February March April May June July August September October November December |
Monthly Production
6,431,304
7,532,360 7,506,180 9,700,064 11,766,040 12,552,188 13,178,264 12,761,628 11,947,804 10,005,248 7,709,636 6,788,848 |
Production Capacity
49,104,000
44,352,000 49,104,000 47,520,000 49,104,000 47,520,000 49,104,000 49,104,000 47,520,000 49,104,000 47,520,000 49,104,000 |
Demand Percentage of Production13%
17% 15% 20% 24% 26% 27% 26% 25% 20% 16% 14% |
This site shall be up-dated as soon as data is recorded and calculated.